  1. D1010 Which of these are not inputs to the Determine Budgets process?





  2.  A project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the project is complete and Actual costs are $ 50,000. What is the Cost Performance Index (CPI) ?





  3.  An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:





  4.  A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called:





  5.  As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-running and under-running budget, milestones due, and milestones met. Which of the following is not a valid technique that you would use for performance-reporting?