  1. F1142 Which is not a tool used in Quality Planning process :





  2.  You are the project manager for a big size project and quality is top priority for this project. You have devoted so much of the project time for planning. Why?





  3.  Quality assurance is:





  4.  The zero defects concept:





  5.  3 sigma is equal to ______ percentage of fall between two control limits.