surepasspmp.com timer

Please Do not press "Submit" at the end of the exam until you are sure of your responses, as your test will be graded immediately.
You can hover your mouse pointer over to see the question ID. Good luck!


  1. H1080 You are working in the US, but have outsourced programming to India and structural engineering to people in Australia. The project doesn't have the budget to bring all the team together, so you will be relying on e-mail, fax, video conference and chat to work together. This is an example of?





  2.  You are managing a project team that is distributed across global locations. You communicate via email on a daily basis and have a telephonic status call once a week. Which of the following statements is valid?





  3.  If there are 10 people working on a project, how many total communication channels are there?





  4.  Which one of the following tools and techniques is NOT part of the Develop Project Team process?





  5.  No matter how good you are in communicating, information distribution to stakeholders as planned is a challenging task. Many tools are used in a project for effective information distribution that includes all of the following EXCEPT: