- Which of the following inaccurately describes a prototype?
A) A prototype is tangible and allows stakeholders to fine-tune their expectations.
B) Requirements from a prototype are usually insufficient to move to the design phase.
C) Prototypes support the concept of progressive elaboration.
D) A prototype is a working model of the expected product.
Your answer=,
Correct answer= ,
Work Sheet:
- As a project manager, you are responsible for determining and delivering the required levels of both grade and quality. Select which of the following statements you disagree with.
A) A product can be of a low quality but high grade.
B) Low quality and Low grade are always a problem.
C) A product can be of a high quality but low grade.
D) Low quality is always a problem but low grade need not always be a problem.
Your answer=,
Correct answer= ,
Work Sheet:
- In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?
A) Functional manager
B) HR manager
C) Team members
D) Project Manager
Your answer=,
Correct answer= ,
Work Sheet:
- A control chart should always contain:
A) Upper and lower warning limits
B) The cumulative average
C) Upper and lower control limits
D) A target value
Your answer=A,
Correct answer= ,
Work Sheet:
- A ______ is a collection of projects or programs grouped together for strategic business needs.
A) Portfolio
B) Management System
C) Enterprise
D) Array
Your answer=A,
Correct answer= ,
Work Sheet: