  1.  You are managing a project that involves work on a film shoot. The editing activity can happen only after the film has been shot. The logical relationship between the editing and shooting of the film can best be described as:

    A) Finish-to-Finish (FF)
    B) Start-to-Start (SS)
    C) Start-to-Finish (SF)
    D) Finish-to-Start (FS)

    Your answer=, Correct answer= , Work Sheet:

  2.  The accuracy of Activity Duration estimates can be improved by considering the amount of risk in the original estimate. The three types of estimates on which three-point estimates are based are:

    A) Budgetary, Ballpark, Order of Magnitude.
    B) Best case scenario, Expected scenario and current scenario.
    C) Most likely, likely, unlikely
    D) Most likely, optimistic, pessimistic

    Your answer=, Correct answer= , Work Sheet:

  3.  After one year of construction, an office building is scheduled to be completed on 30th January. The landscaping work needs to start 15 days prior to completion of the building. Which of the following relationships most likely represents the relationship of the start of landscaping work to the completion of the office building?

    A) Finish-to-start with a 15 day lead
    B) Start-to-finish with a 15 day lead
    C) Finish-to-start with a 15 day lag
    D) Start-to-finish with a 15 day lag

    Your answer=, Correct answer= , Work Sheet:

  4.  The critical path method (CPM) calculates the theoretical early start and finish dates and late start and finish dates. Critical paths have either:

    A) Zero or positive total float
    B) Positive total float
    C) Positive or negative total float
    D) Zero or negative total float

    Your answer=, Correct answer= , Work Sheet:

  5.  While planning the schedule for your project, you frequently refer to the project calendar. The project calendar is:

    A) A calendar containing the days on which various meetings are scheduled within the project team.
    B) A calendar of working days or shifts that establishes those dates on which schedule activities are worked.
    C) A calendar containing the list of days on which the project team members will be on leave or take an off.
    D) A calendar that establishes the dates on which project deliverables are sent to the customer.

    Your answer=, Correct answer= , Work Sheet: