  1.  Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?

    A) Lateral thinking
    B) Six Thinking Hats
    C) Map Out
    D) Brainstorming

    Your answer=, Correct answer= , Work Sheet:

  2.  Which of the following statements is correct?

    A) A collection of unrelated programs can constitute a portfolio.
    B) The scope of a portfolio is typically smaller than that of a program.
    C) A program is a group of unrelated projects.
    D) A program need not consist of projects.

    Your answer=B, Correct answer= , Work Sheet:

  3.  Which tools and techniques are recommended for developing a project team?

    A) Performance assessment, recognition and rewards, and team building
    B) Training, team building, and ground rules
    C) Team building, creating organizational charts, and assessing individual's performance
    D) Setting ground rules and assessing team members based on those rules

    Your answer=, Correct answer= , Work Sheet:

  4.  Pareto's Law states that eighty percent of the ______ are due to twenty percent of the _______. This is also known as the 80/20 rule.

    A) problems/causes
    B) causes/problems
    C) work/effort
    D) effort/work

    Your answer=, Correct answer= , Work Sheet:

  5.  During a weekly staff meeting another project manager, a certified PMP, is reporting that a project he is running completed successfully the night before. However, you know that there are still several large outstanding deliverables. What do you do?

    A) File a complaint with PMI.
    B) Notify the project manager's supervisor, and file a complaint with PMI.
    C) Do nothing.
    D) Notify the project manager's supervisor.

    Your answer=, Correct answer= , Work Sheet: