Note: You can hover cursor to to find the correct answer.

2  (40%) 1 Min 27 Sec

  1.  You are the project manager and you meet with your project team to ensure the project is completed with no deviations from the project requirements.This is part of?

    A) Quality Control
    B) Quality assurance
    C) Plan Quality
    D) All of the above

    Your answer=D, Correct answer= , Work Sheet:

  2.  The zero defects concept:

    A) A. is a performance standard for management
    B) B. is a motivational technique that promotes "doing it right the first time"
    C) C. is used by management to communicate to all employees that everyone should do things right the first time
    D) D. A and C

    Your answer=C, Correct answer= ,

  3.  Quality assurance is:

    A) A. top management's intention regarding quality
    B) B. functions determining implementation of the quality policy
    C) C. actions to provide confidence of satisfying quality requirements
    D) D. responsibilities and processes which implement quality management

    Your answer=D, Correct answer= , Work Sheet:

  4.  3 sigma is equal to ______ percentage of fall between two control limits.

    A) 99.99%
    B) 99.73%
    C) 95.46%
    D) 68.26%

    Your answer=B, Correct answer= , Work Sheet:

  5.  You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________.

    A) Quality Control
    B) Quality assurance
    C) Plan Quality
    D) All of the above

    Your answer=C, Correct answer= , Work Sheet: