- Which of these is not a tool or technique for the Administer Procurements process?
A) Contract change control system
B) Recommended Corrective Action
C) Claims administration
D) Performance reporting
Your answer=,
Correct answer= ,
Work Sheet:
- Pareto's Law states that eighty percent of the ______ are due to twenty percent of the _______. This is also known as the 80/20 rule.
A) problems/causes
B) causes/problems
C) work/effort
D) effort/work
Your answer=A,
Correct answer= ,
Work Sheet:
- During a weekly staff meeting another project manager, a certified PMP, is reporting that a project he is running completed successfully the night before. However, you know that there are still several large outstanding deliverables. What do you do?
A) File a complaint with PMI.
B) Notify the project manager's supervisor, and file a complaint with PMI.
C) Do nothing.
D) Notify the project manager's supervisor.
Your answer=,
Correct answer= ,
Work Sheet:
- In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?
A) Functional manager
B) HR manager
C) Team members
D) Project Manager
Your answer=,
Correct answer= ,
Work Sheet:
- A control chart should always contain:
A) Upper and lower warning limits
B) The cumulative average
C) Upper and lower control limits
D) A target value
Your answer=,
Correct answer= ,
Work Sheet: