  1.  Uncontrolled project scope changes are often referred to as ________ .

    A) Scope creep
    B) Scope verification
    C) Value Added Scope
    D) Scope control

    Your answer=A, Correct answer= , Work Sheet:

  2.  Why must the Verify Scope be completed in a project?

    A) To obtain scope documents from recent similar projects for benchmarking
    B) To determine if the scope is assigned the correct complexity level
    C) To obtain formal acceptance of deliverables by the customer or sponsor
    D) To ensure the project team is all aware of the scope

    Your answer=C, Correct answer= , Work Sheet:

  3.  The WBS is finalized by establishing control accounts for the work packages and a unique identifier from a code of accounts. This provides a structure for hierarchical summation of:

    A) Schedule and requirements information
    B) Cost and requirements information
    C) Cost and resource information
    D) Cost, schedule and resource information

    Your answer=D, Correct answer= , Work Sheet:

  4.  Which of the following is not a Group Creativity Technique used in the Collect Requirements process?

    A) Nominal group technique
    B) Idea diagram
    C) Mind mapping
    D) Affinity diagram

    Your answer=D, Correct answer= , Work Sheet:

  5.  Which of the following processes is not a part of Project Scope Management?

    A) Create WBS
    B) Perform Quality Control
    C) Control Scope
    D) Collect Requirements

    Your answer=B, Correct answer= , Work Sheet: