- If you want to compress a project schedule, what are two of the recommended alternatives to consider?
A) Fast Tracking and Schedule Network Analysis
B) Crashing and Fast Tracking
C) Resource Leveling and What-If Scenario Analysis
D) Crashing and Schedule Network Analysis
Your answer=A,
Correct answer= ,
Work Sheet:
- Which of the following inaccurately describes a prototype?
A) A prototype is tangible and allows stakeholders to fine-tune their expectations.
B) Requirements from a prototype are usually insufficient to move to the design phase.
C) Prototypes support the concept of progressive elaboration.
D) A prototype is a working model of the expected product.
Your answer=,
Correct answer= ,
Work Sheet:
- Which of these is not a tool or technique for the Administer Procurements process?
A) Contract change control system
B) Recommended Corrective Action
C) Claims administration
D) Performance reporting
Your answer=,
Correct answer= ,
Work Sheet:
- A hierarchical structure of resources organized by resource type category and resource type used in resource leveling schedules is known as:
A) Team structure
B) Resource Pool
C) Organization breakdown Structure
D) Resource Breakdown Structure
Your answer=,
Correct answer= ,
Work Sheet:
- In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?
A) Functional manager
B) HR manager
C) Team members
D) Project Manager
Your answer=,
Correct answer= ,
Work Sheet: