  1.  If you want to compress a project schedule, what are two of the recommended alternatives to consider?

    A) Fast Tracking and Schedule Network Analysis
    B) Crashing and Fast Tracking
    C) Resource Leveling and What-If Scenario Analysis
    D) Crashing and Schedule Network Analysis

    Your answer=, Correct answer= , Work Sheet:

  2.  Which of the following statements is correct?

    A) A collection of unrelated programs can constitute a portfolio.
    B) The scope of a portfolio is typically smaller than that of a program.
    C) A program is a group of unrelated projects.
    D) A program need not consist of projects.

    Your answer=, Correct answer= , Work Sheet:

  3.  You are a consulting project manager with over 15 years experience running software development projects. You have been engaged to manage a finance application project for a new customer. However on the first day onsite at the customer's headquarters you are told the project has been cancelled, but there is a need for a project manager to manage a major infrastructure project to deploy a large number of servers and storage devices. The customer asks if you would be interested in leading this project. You have never managed this type of project before but would be interested in the challenge. Which of the follow is the best response?

    A) Do not mention your lack of experience, but ask for more information about the project. After reviewing the information and see that you could probably wing the project, accept the project.
    B) Accept the job with the caveat you can bring in any needed resources to work on the project, then hire a project manager you know that works in this area to handle the implementation details.
    C) Decline the opportunity, citing your lack of experience and knowledge in this area.
    D) Do not mention your lack of experience and accept the job.

    Your answer=, Correct answer= , Work Sheet:

  4.  Which of the following is not a general management technique used to generate different approaches to execute and perform the project work?

    A) Lateral thinking
    B) Six Thinking Hats
    C) Map Out
    D) Brainstorming

    Your answer=, Correct answer= , Work Sheet:

  5.  What is the difference between a histogram and a pareto chart?

    A) A histogram is a less accurate version of a pareto chart.
    B) A histogram is a type of pareto chart.
    C) A pareto chart is a type of histogram.
    D) A histogram and a pareto chart simply different terms for the same technique.

    Your answer=, Correct answer= , Work Sheet: